Some of the work we have done since yesterday morning was to: 1. Install an isolation transformer into the panel feed for the Inverter Room 2. Install the new Inverters onto the wall along with the peripherals 3. Install a power bypass so we could remove the old Inverters and batteries 4. The old batteries were removed 5. The concrete shelf that held one layer of batteries was removed 6. New Batteries finally showed up The old battery room looks like the result of a major earthquake and the wall where we installed the new Inverters needs patched as it was severely damaged...
The new batteries arriving on site is a good thing!
The isolation transformer is located by the Main Panels and Automatic Transfer Switches.
By end of today we hope to have the new battery rack in place and the batteries positioned on it. We will keep you posted.